Project Objectives
To provide an enhanced walking and biking facilities on Bowen Road and to renew traffic signal hardware at the intersection of Bowen Road and Wakesiah Avenue.
Project Details
Construction of raised sidewalk on the southwest side of Bowen Road, bike lanes, and traffic signal hardware upgrades at Wakesiah Avenue will begin in October and is expected to be completed in 12 weeks.
Questions & Answers
Q: How will traffic be impacted?
A: Traffic Control personnel will be on site to ensure that traffic delays are minimized.
Q: Will trees be cut down in Bowen Park?
A: It will be necessary to trim some of the lower branches on trees adjacent to the road, however there is no plan to remove trees as part of this project.
Q: Is this the next phase of the Bowen Road widening?
A: No, Bowen Road will not be widened. This project is to complete the last section of sidewalk on Bowen Road and to add dedicated bike lanes.